Data centers and new power in Washington Parish, LA

250 MW of new power is waiting to connect to the grid in Washington Parish, LA — 2 active requests. Typical wait: 2.4 years. 4 projects are built, 11 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Washington Parish itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Washington Parish

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Washington Parish right now.

250 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 200,000 homes use.
400 MW
has actually been built
4 projects switched on so far.
2.4 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 24%
  • Still waiting 12%
  • Withdrawn 65%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Washington Parish.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

17 requests ever filed
Pending applications
2
of 17 ever filed
Capacity queued
250 MW
requested, not committed
Already built
400 MW
4 projects connected
Built vs decided
26.7%
11 withdrawn
Median wait
2.4 yr
for applications still pending
Connected capacity
599 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4400 MW23.5%
Still waiting2250 MW11.8%
Withdrawn111.3 GW64.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2250 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
BOGALUSA 500 SS - FRANKLIN EHV 500.0kVSolar250 MWwithdrawn2022-09MISO
Angie to Adams Creek 230 kVSolar200 MWcompleted2022-03MISO
Bogslusa 500 kV - Franklin EHV 500 kVSolar200 MWwithdrawn2022-09MISO
BOGALUSA 500 SS - FRANKLIN EHV 500.0kVSolar + battery200 MWwithdrawn2022-09MISO
BOGALUSASolar175 MWwithdrawn2022-09MISO
BOGALUSA - DEXTER SS (CE) 115.0kVSolar150 MWactive2022-09MISO
Barkers Corner - Bogalusa 230 kV LineSolar100 MWwithdrawn2020-06MISO
Talisheek - Bogalusa 230 kV LineSolar100 MWcompleted2020-06MISO
BOGALUSASolar100 MWwithdrawn2021-08MISO
BOGALUSA - TALISHEEK (LAGEN) 230.0kVSolar100 MWactive2026-02MISO
J1564 SubstationSolar100 MWwithdrawn2022-09MISO
Lagen Holton-Franklinton 115kV (J1184)Solar50 MWwithdrawn2019-04MISO
Talisheek - Bogalusa 230 kV LineSolar50 MWwithdrawn2020-06MISO
Barkers Corner - Bogalusa 230 kV LineSolar50 MWwithdrawn2020-06MISO
Lagen Holton-Franklinton 115kV Line TapSolar50 MWcompleted2018-03MISO

How Washington Parish compares

#847 in the US · #17 in LA

Washington Parish ranks #847 of 1,607 US counties by power waiting to connect, and #17 of 31 in Louisiana.

Common questions about power in Washington Parish

How long does it take to get power for a data center in Washington Parish, LA?

The median wait for a project still in the interconnection queue in Washington Parish is 2.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Washington Parish have reached energization and 11 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Washington Parish, LA?

250 MW is currently requested across 2 active interconnection requests, and 400 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Washington Parish, LA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Louisiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Washington Parish — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Washington Parish

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Washington Parish on the map County reports All of Louisiana