Morehouse Parish, LA interconnection queue
6 interconnection applications are pending in Morehouse Parish, LA, requesting 1.2 GW of new generating capacity, as of 15 August 2026. 4 projects have been built here and 17 have been withdrawn since 2017.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Morehouse Parish, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 3 | 750 MW |
| Hybrid | 2 | 260 MW |
| Wind | 1 | 180 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 4 | 475 MW | 14.8% |
| Still pending | 6 | 1.2 GW | 22.2% |
| Withdrawn | 17 | 3.0 GW | 63.0% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| BAXTER WILSON SES SWYD - PERRYVILLE 500 SWYD 500.0kV | Gas | 650 MW | withdrawn | 2025-10 | MISO |
| BAXTER WILSON SES SWYD - PERRYVILLE 500 500 kV (181.1,503.0) | Solar | 500 MW | withdrawn | 2022-09 | MISO |
| BAXTER WILSON SES SWYD - PERRYVILLE 500 SWYD 500.0kV | Solar | 300 MW | active | 2024-04 | MISO |
| DUNN - OAK RIDGE (LA) 115.0kV | Solar | 250 MW | active | 2022-09 | MISO |
| OAK RIDGE (LA) - SWARTZ 115.0kV | Solar | 200 MW | active | 2024-04 | MISO |
| BEEKMAN - NORTH BASTROP 115.0kV | Solar | 200 MW | withdrawn | 2022-09 | MISO |
| GALION - OAK GROVE 115 SUB 115.0kV | Hybrid | 200 MW | withdrawn | 2024-04 | MISO |
| STERLINGTON 115 SWYD - AECC MERIDIAN 115.0kV | Solar | 200 MW | withdrawn | 2025-02 | MISO |
| Crossett North to North Bastrop 115 kV | Solar | 195 MW | withdrawn | 2020-06 | MISO |
| CROSSETT NORTH - BEEKMAN 115.0kV | Solar | 185 MW | completed | 2021-11 | MISO |
| OAK GROVE 115 SUB | Wind | 180 MW | active | 2022-09 | MISO |
| Bastrop to Sterlington 115 kV | Solar | 175 MW | withdrawn | 2022-09 | MISO |
| OAK RIDGE (LA) - STERLINGTON 115 SWYD 115.0kV | Solar | 175 MW | withdrawn | 2024-04 | MISO |
| Dunn - Oak Ridge 115 kV | Hybrid | 175 MW | withdrawn | 2022-09 | MISO |
| Taping the 'Galion / 3GALION (337444)' to 'Oak Grove / 3OAK_GROVE! (337445)' 115 | Hybrid | 160 MW | active | 2022-09 | MISO |
How this county ranks
Morehouse Parish ranks #329 of 1,607 US counties by capacity currently queued, and #3 of 31 in Louisiana.
Other Louisiana counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Bossier Parish | 3 | 1.7 GW |
| Iberville Parish | 3 | 1.7 GW |
| Ouachita Parish | 4 | 1.2 GW |
| Lafayette Parish | 3 | 943 MW |
| Jefferson Davis Parish | 5 | 890 MW |
| Rapides Parish | 3 | 830 MW |
| St. Landry Parish | 4 | 818 MW |
| Richland Parish | 2 | 750 MW |
Go deeper on Morehouse Parish
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Morehouse Parish on the map County reports All of Louisiana