Data centers and new power in Rapides Parish, LA

830 MW of new power is waiting to connect to the grid in Rapides Parish, LA — 3 active requests. Typical wait: 4.1 years. 0 projects are built, 12 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Rapides Parish itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Rapides Parish

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Rapides Parish right now.

830 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 664,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 20%
  • Withdrawn 80%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Rapides Parish.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

15 requests ever filed
Pending applications
3
of 15 ever filed
Capacity queued
830 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
12 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
1.8 GW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting3830 MW20.0%
Withdrawn121.7 GW80.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar3830 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
East Leesville-Rodemacher 230 KVSolar400 MWwithdrawn2022-09MISO
HinestonSolar350 MWactive2022-09MISO
Cooper - Leesville 138.0kVSolar280 MWactive2022-09MISO
EAST LEESVILLE -RODEMACHER 230Solar250 MWwithdrawn2022-09MISO
Cocodrie - Hineston 230kV lineSolar200 MWwithdrawn2022-09MISO
Rapides - Rodemacher 230 kV Line TapSolar200 MWwithdrawn2019-04MISO
HinestonSolar200 MWactive2024-04MISO
Cocodrie-Forest Hill 230kVSolar125 MWwithdrawn2022-09MISO
East Leesville - Rodemacher 230.0kVSolar100 MWwithdrawn2024-04MISO
Donahue-Marksville 138kVSolar100 MWwithdrawn2022-09MISO
RodemacherSolar100 MWwithdrawn2021-12MISO
Shady Oaks - Coughlin 138kV LineNot stated52 MWwithdrawn2016-05MISO
Rapides - Rodemacher 230 kV Line TapSolar50 MWwithdrawn2019-04MISO
Shady Oaks (Bus# 500780) to Coughlin (Bus# 500230)Solar50 MWwithdrawn2021-09MISO
Rapides 230kV SubstationSolar49 MWwithdrawn2022-09MISO

How Rapides Parish compares

#459 in the US · #7 in LA

Rapides Parish ranks #459 of 1,607 US counties by power waiting to connect, and #7 of 31 in Louisiana.

Common questions about power in Rapides Parish

How long does it take to get power for a data center in Rapides Parish, LA?

The median wait for a project still in the interconnection queue in Rapides Parish is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Rapides Parish have reached energization and 12 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Rapides Parish, LA?

830 MW is currently requested across 3 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Rapides Parish, LA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Louisiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Rapides Parish — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.