Ohio County, KY interconnection queue
1 interconnection applications are pending in Ohio County, KY, requesting 100 MW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 6 have been withdrawn since 2008.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Ohio County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 1 | 100 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 1 | 100 MW | 14.3% |
| Withdrawn | 6 | 475 MW | 85.7% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| LGE-GIS-2021-003 | Solar | 150 MW | withdrawn | 2021-01 | LGE-KU |
| BR Tap -- New Hardinsburg 161kV | Hybrid | 100 MW | withdrawn | 2022-03 | MISO |
| WILSON | Solar | 100 MW | active | 2022-09 | MISO |
| 345 kV Wilson Substation | Hybrid | 92 MW | withdrawn | 2021-11 | MISO |
| 345 kV Wilson Substation | Hybrid | 78 MW | withdrawn | 2021-10 | MISO |
| Wilson EHV | Hybrid | 50 MW | withdrawn | 2021-11 | MISO |
| LGE-GIS-2008-002 | Other | 5 MW | withdrawn | 2008-11 | LGE-KU |
How this county ranks
Ohio County ranks #1087 of 1,607 US counties by capacity currently queued, and #21 of 37 in Kentucky.
Other Kentucky counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Jefferson County | 7 | 3.2 GW |
| Muhlenberg County | 6 | 1.4 GW |
| Trimble County | 9 | 925 MW |
| Mercer County | 6 | 922 MW |
| Henderson County | 3 | 800 MW |
| Fleming County | 4 | 548 MW |
| Mccraken | 3 | 466 MW |
| Martin County | 2 | 300 MW |
Go deeper on Ohio County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.