Data centers and new power in New Castle County, DE

134 MW of new power is waiting to connect to the grid in New Castle County, DE — 1 active requests. Typical wait: 5.5 years. 25 projects are built, 32 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside New Castle County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in New Castle County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in New Castle County right now.

134 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 107,000 homes use.
4.8 GW
has actually been built
25 projects switched on so far.
5.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 40%
  • Still waiting 2%
  • Withdrawn 52%
  • Paused 6%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for New Castle County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

62 requests ever filed
Pending applications
1
of 62 ever filed
Capacity queued
134 MW
requested, not committed
Already built
4.8 GW
25 projects connected
Built vs decided
43.9%
32 withdrawn
Median wait
5.5 yr
for applications still pending
Connected capacity
2.3 GW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built254.8 GW40.3%
Still waiting1134 MW1.6%
Withdrawn326.8 GW51.6%
Paused4—6.5%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar1134 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Hay Road 230kVNatural gas856 MWwithdrawn2011-04PJM
Cartanza 230kVNatural gas760 MWwithdrawn2015-02PJM
Red Lion 500kVNatural gas711 MWwithdrawn2000-07PJM
EdgemoorNatural gas565 MWwithdrawn2001-12PJM
EdgemoorNatural gas565 MWwithdrawn2002-09PJM
Hay RoadNatural gas565 MWcompleted2007-09PJM
Red Lion 500kVNatural gas565 MWcompleted2007-09PJM
Red Lion 500kVNatural gas550 MWwithdrawn2000-07PJM
Red Lion 500kVNatural gas545 MWcompleted1999-11PJM
EdgemoorNatural gas521 MWcompleted2000-04PJM
Hawkins Gate / Oak Grove 230kVNatural gas450 MWwithdrawn1999-03PJM
Edgemoor 230kVNatural gas450 MWcompleted2007-02PJM
Hay Road 230kV 1Natural gas402 MWwithdrawn2010-10PJM
Hay Road 230kVNatural gas371 MWwithdrawn2014-07PJM
Cartanza 230kVNatural gas309 MWcompleted2010-08PJM

How New Castle County compares

#1043 in the US · #1 in DE

New Castle County ranks #1043 of 1,607 US counties by power waiting to connect, and #1 of 3 in Delaware.

CountyWaitingCapacity queued
Kent County390 MW
Sussex County175 MW

Common questions about power in New Castle County

How long does it take to get power for a data center in New Castle County, DE?

The median wait for a project still in the interconnection queue in New Castle County is 5.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 25 projects in New Castle County have reached energization and 32 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in New Castle County, DE?

134 MW is currently requested across 1 active interconnection requests, and 4.8 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is New Castle County, DE a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Delaware policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving New Castle County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on New Castle County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open New Castle County on the map County reports All of Delaware