WAPA-RM interconnection queue

19 interconnection requests are active in WAPA-RM, totalling 4.6 GW, as of 15 August 2026. Of the 110 requests ever filed here, 3 were built and 88 were withdrawn — a build rate of 3.3% on decided applications.

Active requests
19
of 110 ever filed
Capacity queued
4.6 GW
requested, not committed
Built vs decided
3.3%
3 built, 88 withdrawn
Median wait so far
3.7 yr
for requests still active
Median time to build
2.4 yr
request to commercial operation

Source: the WAPA-RM interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in WAPA-RM, by fuel

FuelProjectsCapacity requested
Solar112.4 GW
Wind72.1 GW
Battery190 MW

Largest active requests

ProjectFuelCapacityCountyStateFiled
2023-G5.2Solar500 MW2023-06
2025-G3Wind500 MW2025-08
2025-G4Wind500 MW2025-08
2023-G1Solar400 MW2022-10
2025-G7Wind400 MW2025-11
2018-G6Solar360 MW2018-09
2019-G1Wind252 MW2018-11
2019-G2Wind252 MW2018-11
2025-G1Solar250 MW2024-01
2024-G4Solar170 MW2024-11
2019-G3Solar150 MW2018-12
2023-G2Solar150 MW2022-11
2023-G3Solar150 MW2022-11
2017-G2Wind130 MW2017-01
2025-G5Solar100 MW2025-09