WAPA-RM interconnection queue
19 interconnection requests are active in WAPA-RM, totalling 4.6 GW, as of 15 August 2026. Of the 110 requests ever filed here, 3 were built and 88 were withdrawn — a build rate of 3.3% on decided applications.
Active requests
19
of 110 ever filed
Capacity queued
4.6 GW
requested, not committed
Built vs decided
3.3%
3 built, 88 withdrawn
Median wait so far
3.7 yr
for requests still active
Median time to build
2.4 yr
request to commercial operation
Source: the WAPA-RM interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.
What is queued in WAPA-RM, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 11 | 2.4 GW |
| Wind | 7 | 2.1 GW |
| Battery | 1 | 90 MW |
Largest active requests
| Project | Fuel | Capacity | County | State | Filed |
|---|---|---|---|---|---|
| 2023-G5.2 | Solar | 500 MW | — | — | 2023-06 |
| 2025-G3 | Wind | 500 MW | — | — | 2025-08 |
| 2025-G4 | Wind | 500 MW | — | — | 2025-08 |
| 2023-G1 | Solar | 400 MW | — | — | 2022-10 |
| 2025-G7 | Wind | 400 MW | — | — | 2025-11 |
| 2018-G6 | Solar | 360 MW | — | — | 2018-09 |
| 2019-G1 | Wind | 252 MW | — | — | 2018-11 |
| 2019-G2 | Wind | 252 MW | — | — | 2018-11 |
| 2025-G1 | Solar | 250 MW | — | — | 2024-01 |
| 2024-G4 | Solar | 170 MW | — | — | 2024-11 |
| 2019-G3 | Solar | 150 MW | — | — | 2018-12 |
| 2023-G2 | Solar | 150 MW | — | — | 2022-11 |
| 2023-G3 | Solar | 150 MW | — | — | 2022-11 |
| 2017-G2 | Wind | 130 MW | — | — | 2017-01 |
| 2025-G5 | Solar | 100 MW | — | — | 2025-09 |