PNM interconnection queue

80 interconnection requests are active in PNM, totalling 13.4 GW, as of 15 August 2026. Of the 356 requests ever filed here, 45 were built and 224 were withdrawn — a build rate of 16.7% on decided applications.

Active requests
80
of 356 ever filed
Capacity queued
13.4 GW
requested, not committed
Built vs decided
16.7%
45 built, 224 withdrawn
Median wait so far
5.1 yr
for requests still active
Median time to build
3.7 yr
request to commercial operation

Source: the PNM interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in PNM, by fuel

FuelProjectsCapacity requested
Solar427.1 GW
Battery203.2 GW
Wind92.2 GW
Gas5611 MW
Hydrogen1210 MW
Geothermal378 MW

Where PNM’s queue sits

StateApplicationsCapacity pending
New Mexico35613.4 GW

Largest active requests

ProjectFuelCapacityCountyStateFiled
IA-PNM-2019-11Solar500 MWSan Juan CountyNM2019-04
IA-PNM-2023-11Battery500 MWValencia CountyNM2023-01
IA-PNM-2016-02Wind402 MWTorrance CtyNM2016-05
IA-PNM-2020-04Solar400 MWBernalillo CountyNM2020-01
IA-PNM-2025-09Battery400 MWValencia CountyNM2025-03
IA-PNM-2025-19Wind400 MWTorrance CountyNM2025-03
IA-PNM-2017-13Solar400 MWSan Juan CountyNM2017-10
IA-PNM-2025-10Solar400 MWBernalillo CountyNM2025-03
IA-PNM-2025-01Solar371 MWValencia CountyNM2025-01
IA-PNM-2021-10Solar300 MWBernalillo CountyNM2021-07
IA-PNM-2023-07Solar300 MWSanta Fe CountyNM2023-01
IA-PNM-2023-08Wind300 MWGuadalupe CountyNM2022-12
IA-PNM-2023-01Wind250 MWCibola CountyNM2022-10
IA-PNM-2023-30Solar250 MWSanta Fe CountyNM2023-09
IA-PNM-2025-06Solar250 MWBernalillo CountyNM2025-03

PNM on the map