Dominion interconnection queue
35 interconnection requests are active in Dominion, totalling 4.1 GW, as of 15 August 2026. Of the 118 requests ever filed here, 0 were built and 83 were withdrawn — a build rate of 0.0% on decided applications.
Active requests
35
of 118 ever filed
Capacity queued
4.1 GW
requested, not committed
Built vs decided
0.0%
0 built, 83 withdrawn
Source: the Dominion interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.
What is queued in Dominion, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 19 | 2.1 GW |
| Gas | 12 | 1.6 GW |
| Battery | 3 | 374 MW |
| Hydro | 1 | 48 MW |
Where Dominion’s queue sits
| State | Applications | Capacity pending |
|---|---|---|
| South Carolina | 118 | 4.1 GW |
Largest active requests
| Project | Fuel | Capacity | County | State | Filed |
|---|---|---|---|---|---|
| 20240829009 | Gas | 338 MW | Colleton County | SC | — |
| 20240829010 | Gas | 338 MW | Colleton County | SC | — |
| 20240829011 | Gas | 338 MW | Colleton County | SC | — |
| 20240829001 | Solar | 250 MW | Richland County | SC | — |
| 20240829004 | Solar | 250 MW | Colleton County | SC | — |
| 20190729002 | Solar | 200 MW | Colleton County | SC | — |
| 20230829013 | Battery | 199 MW | Berkeley County | SC | — |
| 20181030001 | Solar | 160 MW | Charleston County | SC | — |
| 20211104001 | Gas | 158 MW | Jasper County | SC | — |
| 20181030002 | Solar | 103 MW | Charleston County | SC | — |
| 20210310001 | Solar | 100 MW | Orangeburg County | SC | — |
| 20230825001 | Solar | 100 MW | Colleton County | SC | — |
| 20250918001 | Battery | 100 MW | Colleton County | SC | — |
| 20200824001 | Solar | 86 MW | Bamberg County | SC | — |
| 20220316001 | Solar | 80 MW | Aiken County | SC | — |