BHCT interconnection queue

9 interconnection requests are active in BHCT, totalling 1.0 GW, as of 15 August 2026. Of the 51 requests ever filed here, 9 were built and 32 were withdrawn — a build rate of 22.0% on decided applications.

Active requests
9
of 51 ever filed
Capacity queued
1.0 GW
requested, not committed
Built vs decided
22.0%
9 built, 32 withdrawn
Median wait so far
4.2 yr
for requests still active
Median time to build
2.5 yr
request to commercial operation

Source: the BHCT interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in BHCT, by fuel

FuelProjectsCapacity requested
Solar8964 MW
Battery150 MW

Where BHCT’s queue sits

StateApplicationsCapacity pending
Colorado511.0 GW

Largest active requests

ProjectFuelCapacityCountyStateFiled
BHCT G49Solar200 MWPueblo CountyCO2024-06
BHCT G33Solar199 MWPueblo CountyCO2022-06
BHCT G35Solar150 MWPueblo CountyCO2022-08
BHCT G32Solar100 MWPueblo CountyCO2022-04
BHCT G52Solar100 MWPueblo CountyCO2024-06
BHCT G21Solar80 MWPueblo CountyCO2017-01
BHCT G28Solar75 MWPueblo CountyCO2020-02
BHCT G19Solar60 MWPueblo CountyCO2015-04
BHCT G50Battery50 MWPueblo CountyCO2024-06