Data centers and new power in Washington County, RI

205 MW of new power is waiting to connect to the grid in Washington County, RI — 1 active requests. Typical wait: 5.1 years. 3 projects are built, 27 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Washington County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Washington County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Washington County right now.

205 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 164,000 homes use.
50 MW
has actually been built
3 projects switched on so far.
5.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 10%
  • Still waiting 3%
  • Withdrawn 87%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Washington County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

31 requests ever filed
Pending applications
1
of 31 ever filed
Capacity queued
205 MW
requested, not committed
Already built
50 MW
3 projects connected
Built vs decided
10.0%
27 withdrawn
Median wait
5.1 yr
for applications still pending
Connected capacity
189 MW
indicator, see note

Source: interconnection queues published by ISONE. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built350 MW9.7%
Still waiting1205 MW3.2%
Withdrawn271.6 GW87.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1205 MW

Key dates for projects here

1 dated · next closes 2026-11-19 (ISONE)
QueueWhat closesClosesStanding
ISONEISO-NE cluster request window
Cluster study under OATT Schedules 22, 23 and 25.
2026-11-19disputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
WindWind536 MWwithdrawn2010-02ISONE
WindWind385 MWwithdrawn2008-05ISONE
Battery StorageBatteries313 MWwithdrawn2024-06ISONE
Battery StorageBatteries205 MWactive2021-09ISONE
Battery StorageBatteries180 MWwithdrawn2019-04ISONE
Wood River Substation - Western RI DER Study #3Solar49 MWwithdrawn2024-08ISONE
Wood River - NG WRI DG Area Study #2 >5 MWSolar34 MWwithdrawn2020-08ISONE
Block Island Wind FarmWind29 MWcompleted2013-01ISONE
WindWind29 MWwithdrawn2009-08ISONE
WindWind20 MWwithdrawn2009-02ISONE
Alton SolarSolar14 MWcompleted2017-11ISONE
Wood River - NG WRI DG Area Study #2 <5 MWSolar10 MWwithdrawn2020-08ISONE
SolarSolar8 MWwithdrawn2018-08ISONE
Wood River Substation - NG Western RI DG Area StudySolar8 MWwithdrawn2020-03ISONE
Chase Hill - NG WRI DG Area Study #2 <5 MWSolar7 MWwithdrawn2020-08ISONE

How Washington County compares

#897 in the US · #1 in RI

Washington County ranks #897 of 1,607 US counties by power waiting to connect, and #1 of 4 in Rhode Island.

CountyWaitingCapacity queued
Kent County00 MW
Newport County00 MW
Providence County00 MW

Common questions about power in Washington County

How long does it take to get power for a data center in Washington County, RI?

The median wait for a project still in the interconnection queue in Washington County is 5.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Washington County have reached energization and 27 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Washington County, RI?

205 MW is currently requested across 1 active interconnection requests, and 50 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Washington County, RI a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Rhode Island policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Washington County — ISONE — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Washington County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Washington County on the map County reports All of Rhode Island