Data centers and new power in Sandoval Cty, NM

640 MW of new power is waiting to connect to the grid in Sandoval Cty, NM — 6 active requests. Typical wait: 7.5 years. 5 projects are built, 5 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Sandoval Cty itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Sandoval Cty

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Sandoval Cty right now.

640 MW
of new power is waiting to connect
6 projects asked. Not yet approved. Roughly what 512,000 homes use.
359 MW
has actually been built
5 projects switched on so far.
7.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 31%
  • Still waiting 38%
  • Withdrawn 31%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Sandoval Cty.

What kind of power is asking to connect

  • Batteries 62%
  • Solar 38%

By capacity requested. Data as of 14 October 2026.

All the numbers

16 requests ever filed
Pending applications
6
of 16 ever filed
Capacity queued
640 MW
requested, not committed
Already built
359 MW
5 projects connected
Built vs decided
50.0%
5 withdrawn
Median wait
7.5 yr
for applications still pending
Connected capacity
467 MW
indicator, see note

Source: interconnection queues published by PNM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built5359 MW31.2%
Still waiting6640 MW37.5%
Withdrawn5325 MW31.2%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries3400 MW
Solar3240 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
IA-PNM-2023-02Batteries200 MWactive2023-01PNM
IA-PNM-2017-02Solar150 MWwithdrawn2017-01PNM
IA-PNM-2017-03Solar150 MWwithdrawn2017-01PNM
IA-PNM-2021-16Batteries150 MWactive2021-07PNM
NMRD Data Center IVSolar140 MWactive2017-01PNM
Sky Ranch Solar / Sky Ranch Energy StorageSolar120 MWcompleted2017-01PNM
EXUS NM Data Center IIISolar100 MWcompleted2017-01PNM
Sky Ranch Solar / Sky Ranch Energy StorageSolar70 MWcompleted2017-09PNM
NMRD Data Center IIISolar60 MWcompleted2015-08PNM
IA-PNM-2017-06Solar50 MWactive2017-01PNM
IA-PNM-2017-07Solar50 MWactive2017-01PNM
IA-PNM 2022-10Batteries50 MWactive2022-04PNM
SGI-PNM-2016-02Solar10 MWwithdrawn2016-11PNM
SGI-PNM-2016-03Solar10 MWwithdrawn2016-11PNM
SGI-PNM-2013-03Solar9 MWcompleted2013-05PNM

How Sandoval Cty compares

#538 in the US · #13 in NM

Sandoval Cty ranks #538 of 1,607 US counties by power waiting to connect, and #13 of 21 in New Mexico.

CountyWaitingCapacity queued
Bernalillo Cty213.9 GW
Roosevelt County92.4 GW
Valencia Cty112.2 GW
San Juan County92.1 GW
Santa Fe County91.6 GW
Torrence51.2 GW
Lea County91.1 GW
Doña Ana Cty7953 MW

Common questions about power in Sandoval Cty

How long does it take to get power for a data center in Sandoval Cty, NM?

The median wait for a project still in the interconnection queue in Sandoval Cty is 7.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 5 projects in Sandoval Cty have reached energization and 5 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Sandoval Cty, NM?

640 MW is currently requested across 6 active interconnection requests, and 359 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Sandoval Cty, NM a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our New Mexico policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Sandoval Cty — PNM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Sandoval Cty

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.