Data centers and new power in Lancaster County, NE
3.3 GW of new power is waiting to connect to the grid in Lancaster County, NE — 17 active requests. Typical wait: 5.4 years. 0 projects are built, 17 withdrawn. Data as of 14 October 2026.
How far is it from your house?
Google Lincoln, run by Google, is in Lancaster County and uses about as much electricity as 113,000 homes.
69 public schools are within 5 miles of it, 7 within one mile. Counted from the facility, not from any home. School list: US Department of Education.
What is happening with electricity in Lancaster County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Lancaster County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Lancaster County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
35 requests ever filed
Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still waiting | 17 | 3.3 GW | 48.6% |
| Withdrawn | 17 | 4.5 GW | 48.6% |
| Paused | 1 | — | 2.9% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Natural gas | 6 | 1.8 GW |
| Solar | 9 | 1.0 GW |
| Wind | 2 | 428 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| SPP | SPP 2028 CPP Interconnection Cluster Study (ICS) application window Definitive Interconnection System Impact Study cluster, post Order 2023 compliance. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| GEN-2007-011N02 | Coal | 600 MW | withdrawn | 2007-03 | SPP |
| GEN-2024-021 | Natural gas | 540 MW | active | 2024-10 | SPP |
| GEN-2019-007 | Solar | 500 MW | withdrawn | 2019-04 | SPP |
| GEN-2023-224 | Natural gas | 478 MW | active | 2023-10 | SPP |
| GEN-2007-011N01 | Coal | 400 MW | withdrawn | 2007-03 | SPP |
| GEN-2018-066 | Solar | 400 MW | withdrawn | 2018-10 | SPP |
| GEN-2024-020 | Natural gas | 390 MW | active | 2024-10 | SPP |
| GEN-2017-181 | Wind | 300 MW | active | 2017-11 | SPP |
| GEN-2021-060 | Wind | 300 MW | withdrawn | 2021-04 | SPP |
| GEN-2022-198 | Solar | 300 MW | withdrawn | 2023-02 | SPP |
| GEN-2021-043 | Solar | 250 MW | active | 2021-04 | SPP |
| GEN-2021-073 | Solar | 240 MW | withdrawn | 2021-05 | SPP |
| GEN-2022-210 | Solar | 240 MW | withdrawn | 2023-03 | SPP |
| GEN-2017-055 | Solar | 228 MW | withdrawn | 2017-05 | SPP |
| GEN-2021-049 | Solar | 225 MW | active | 2021-04 | SPP |
How Lancaster County compares
#99 in the US · #1 in NE
Lancaster County ranks #99 of 1,607 US counties by power waiting to connect, and #1 of 25 in Nebraska.
| County | Waiting | Capacity queued |
|---|---|---|
| Cass County | 9 | 2.3 GW |
| Gage County | 6 | 1.5 GW |
| Burt County | 4 | 1.1 GW |
| Custer County | 2 | 500 MW |
| Lincoln County | 2 | 456 MW |
| Douglas County | 3 | 450 MW |
| Washington County | 2 | 300 MW |
| Sarpy County | 1 | 273 MW |
Common questions about power in Lancaster County
How long does it take to get power for a data center in Lancaster County, NE?
The median wait for a project still in the interconnection queue in Lancaster County is 5.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Lancaster County have reached energization and 17 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Lancaster County, NE?
3.3 GW is currently requested across 17 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Lancaster County, NE a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Nebraska policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Lancaster County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Lancaster County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Lancaster County on the map County reports All of Nebraska