Data centers and new power in Whiteside County, IL
746 MW of new power is waiting to connect to the grid in Whiteside County, IL — 3 active requests. Typical wait: 6.0 years. 1 projects are built, 7 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Whiteside County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Whiteside County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Whiteside County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Whiteside County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
11 requests ever filed
Source: interconnection queues published by MISO, PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 0 MW | 9.1% |
| Still waiting | 3 | 746 MW | 27.3% |
| Withdrawn | 7 | 1.1 GW | 63.6% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 2 | 555 MW |
| Wind | 1 | 191 MW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| PJM | Dominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1… | No date published yet | disputed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 11 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Garden Plain 138 kV | Batteries | 365 MW | withdrawn | 2022-03 | PJM |
| SUB 39 - CORDOVA 345.0kV | Solar | 300 MW | active | 2022-09 | MISO |
| Garden Plain 138 kV | Wind | 300 MW | withdrawn | 2022-03 | PJM |
| Cordova 345 kV | Solar | 255 MW | active | 2020-10 | PJM |
| Quad Cities - Sterling Steel 345 kV | Wind | 212 MW | withdrawn | 2021-03 | PJM |
| Garden Plain 138 kV | Wind | 191 MW | active | 2019-09 | PJM |
| Garden Plain - Rock Falls 138 kV | Solar | 100 MW | withdrawn | 2022-09 | PJM |
| Rock Falls-Garden Plains | Solar | 68 MW | withdrawn | 2018-03 | PJM |
| Normandy | Solar | 17 MW | withdrawn | 2018-01 | PJM |
| Whiteside County | Batteries | 0 MW | completed | 2020-07 | PJM |
| Quad Cities 345kV | Not stated | — | withdrawn | 2006-07 | PJM |
How Whiteside County compares
#495 in the US · #32 in IL
Whiteside County ranks #495 of 1,607 US counties by power waiting to connect, and #32 of 64 in Illinois.
| County | Waiting | Capacity queued |
|---|---|---|
| Lee County | 12 | 6.4 GW |
| Will County | 5 | 4.3 GW |
| McLean County | 11 | 2.9 GW |
| Ogle County | 5 | 2.9 GW |
| LaSalle County | 7 | 2.8 GW |
| Christian County | 8 | 2.3 GW |
| Peoria County | 7 | 2.1 GW |
| Tazewell County | 10 | 1.9 GW |
Common questions about power in Whiteside County
How long does it take to get power for a data center in Whiteside County, IL?
The median wait for a project still in the interconnection queue in Whiteside County is 6.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Whiteside County have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Whiteside County, IL?
746 MW is currently requested across 3 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Whiteside County, IL a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Illinois policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Whiteside County — MISO, PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.