Data centers and new power in Fayette County, IL
820 MW of new power is waiting to connect to the grid in Fayette County, IL — 7 active requests. Typical wait: 2.5 years. 3 projects are built, 2 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Fayette County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Fayette County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Fayette County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Fayette County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
12 requests ever filed
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 3 | 349 MW | 25.0% |
| Still waiting | 7 | 820 MW | 58.3% |
| Withdrawn | 2 | 249 MW | 16.7% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 6 | 753 MW |
| Wind | 1 | 67 MW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 12 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Coffeen North-Ramsey East-4557 | Solar | 250 MW | active | 2024-03 | MISO |
| Otego 138kV | Solar + battery | 150 MW | withdrawn | 2022-09 | MISO |
| Ramsey East 138kV bus | Solar | 150 MW | completed | 2020-06 | MISO |
| 4OTEGO - 4KINMUNDY 138.0kV | Solar | 113 MW | active | 2024-04 | MISO |
| Ramsey East 138 kV | Solar | 100 MW | active | 2025-01 | MISO |
| Ramsey East 138kV Substation | Solar | 100 MW | completed | 2020-06 | MISO |
| Ramsey East 138 sub (co-located with Dressor and Switchgrass) | Solar | 100 MW | active | 2022-09 | MISO |
| Ramsey | Solar | 100 MW | active | 2025-07 | MISO |
| Ramsey East 138kV Substation | Solar | 99 MW | completed | 2017-06 | MISO |
| S1030 | Not stated | 99 MW | withdrawn | 2022-06 | MISO |
| A Tap on Kinmundy-Otego 138kv line | Solar | 90 MW | active | 2022-08 | MISO |
| 7COFFEN N - 7RAMSEY 345.0kV | Wind | 67 MW | active | 2025-03 | MISO |
How Fayette County compares
#467 in the US · #28 in IL
Fayette County ranks #467 of 1,607 US counties by power waiting to connect, and #28 of 64 in Illinois.
| County | Waiting | Capacity queued |
|---|---|---|
| Lee County | 12 | 6.4 GW |
| Will County | 5 | 4.3 GW |
| McLean County | 11 | 2.9 GW |
| Ogle County | 5 | 2.9 GW |
| LaSalle County | 7 | 2.8 GW |
| Christian County | 8 | 2.3 GW |
| Peoria County | 7 | 2.1 GW |
| Tazewell County | 10 | 1.9 GW |
Common questions about power in Fayette County
How long does it take to get power for a data center in Fayette County, IL?
The median wait for a project still in the interconnection queue in Fayette County is 2.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Fayette County have reached energization and 2 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Fayette County, IL?
820 MW is currently requested across 7 active interconnection requests, and 349 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Fayette County, IL a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Illinois policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Fayette County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Fayette County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.